CNN News L3Harris notified the FAA on November 9 that it planned to carry out maintenance, replacing a router, at a remote FAA facility in El Dorado, Arkansas, with work set to begin at 9 a.m. on Friday, November 13, one of the sources said.
Four days after the notice, the L3Harris worker arrived.
Even the time of day the work was scheduled raised eyebrows, given it was at a time of heavy air traffic. The sources say FAA technicians were not consulted about the best time to carry out this work at this facility.
By that Friday afternoon, the new router was connected and the L3Harris contractor had left the site with no idea of the chaos that was beginning to unfold, the source said.
Hours later, FAA technicians got a call telling them to return to the site to escort the L3Harris engineer back into the facility. The agency scrambled to find the closest available staff to let him in. Hours had passed between the time the engineer had left and the time he returned to retrieve the router, the source said.
A former FAA technician told CNN that, for agency technicians, checking in with air traffic controllers before leaving a site is standard practice. It’s not clear if the L3Harris engineer took this step.
“As a technician, anytime when I was out there … and I did anything, anything at all to the equipment before I left, I would call up the TRACON or the center or the tower, whatever controllers that had the services that I was providing on that equipment. And I would say, ‘I’m getting ready to leave. Everything look good? Everything okay? You got everything?’ They’d be like, ‘yep,’” the former technician said. “It’s just a practice that you do.”
In the immediate aftermath of the ground stop, Duffy was sharply critical of L3Harris, making a point of calling them out in his public remarks.
“We need L3Harris or whoever provided that router to us to do a better job,” Duffy said during his Saturday press conference. “Many of our contractors, many or our partners, they take our money and they provide really poor service to us. Full stop.”
Yet by Tuesday, Bedford sounded a different tone toward L3Harris.
At a news conference, Bedford described the L3Harris contractor who replaced the router as a “highly trained certified engineer, former Air Force veteran, I’m told a generally competent guy doing the work that he has done dozens and dozens of times before.”
Asked what oversight the FAA provides when contractors work at FAA facilities, Bedford also said, “There is a comprehensive risk management process with every installation. And that installation happens whether it’s with a contractor or with an FAA employee.”
Days earlier, Duffy had defended the timing of the work, pointing out that it was at a remote location. He said he didn’t expect the kind of impact seen last Friday at “smaller locations.”