Merrifield: Q4’13 became Q1’14
14nm production:
HVM in Q1’14 became Q3’14 (with yield parity in H2’16)
Broadwell-Y: Q2’14 became Q4’14
Moorefield: Q2’14 became Q4’14 (Only major design win, ZenPhone 2 w/XMM7260, launched in Q1’15.)
Cherry Trail: Q3’14 (mid’14) became Q4’14 became Q2’15
Broadwell-U: Q3’14 became Q1’15
SoFIA 3G (28nm): Q4’14 became Q2’15
Broadwell-C: Q1’15 became Q2’15 (mid’15)
Silicon photonics*: Q1’15 became Q3’16
Skylake-S/-H: Q2’15 became Q3’15 became Q4’15
Willow Trail (aka Morganfield SoC for tablets): Q2’15 became canceled
Morganfield SoC (2.7GHz 14nm QC Goldmont w/Gen9): Q2’15 became canceled (Q4’15 for Android)
Broxton: Q3’15 (mid-‘15) became Q4’16 became canceled
XMM 7360: Q3’15 became Q4’15. “First commercial devices”: H2’15 became Q3’16
SoFIA LTE (28nm w/Spreadtrum): Q3’15 (mid’15) became Q2’16 became canceled
Skylake-U: Q3’15 (mid’15) became Q4’15
Broadwell-E HEDT: Q4’15 became Q1’16 became Q2’16 (mid-’16)
Apollo Lake: Q4’15 became Q3’16
Xeon Phi Knights Landing: H2’15 became Q2’16
Associated with KL also Omni-Path Architecture and Hybrid Memory Cube: H2’15 became Q2’16
10nm: Q4’15 became Q3’17
3D NAND: H2’15 became Q3’16
3D XPoint: 2016 became Q4’16 became mid-‘17
Riverton (low-end 14nm Airmont with 4G modem): Q1’16 became canceled
Broadwell-EP/EX: Q1’16 became Q3’16 (before that planned for 2015
Kaby Lake-U/Y: Q3’16 became Q4’16
Kaby Lake-S/-H: Q4’16 became Q1’17
Skylake-S GT4+4e: Q4’16 became canceled (65W; 35W version considered but not greenlit)
Cannonlake-U/-Y: H2’16 became Q3’17 became Q4’17 became Q1’18 (volume)
Cannonlake-H/-S: 2016 became canceled
SoFIA 14nm w/Spreadtrum: H2’16 became Q3’17
SoFIA LTE2 14nm: Q4’16 became Q3’17 became canceled, along with it the…
Integrated 14nm modem (XMM 7560): Q4’16 became Q3’18 [per BK, no clear roadmap found]
Skylake-EP/EX (Purley): Q2’17 became Q3’17 (mid-’17) (before that planned for H2’16)
Skylake-X: Q2’17 became Q3’17
Apache Pass (3D XPoint DIMM for data center along with Purley): Q2’17 became cancelled
Kaby Lake-X: Q2’17 became Q3’17
Gemini Lake: Q4’17 will become ???
Knights Hill: Never formally disclosed, but possibly H2’17 became H1’19
Omni-Path 2nd gen: Along with Knights Hill
Coffee Lake-H/-U: Q2’18 became H2’18 [confirmation needed]
Cannonlake-EP/EX: 2018 became canceled
Icelake: 2018 per PAO, possibly delayed until 2019?
Tigerlake: 2019 per PAO, possibly delayed until 2020?