Management is pushing for all metrics in various reports to look pristine. One project had a tasks at 100%, which was questioned as the project is most likely, with accurate reporting, in a red status. Response was that the initial jobs or tasks were ran. When it was pointed out that many of those items were incomplete still, the response was well we listed that on another sheet. Got it. Hiding the real results so the reports look good. Never mind that the overall project will fail.
Told today to close out a project that was marked as on hold. Asked why and how to track. Oh just note it yourself, maybe with a stick on note. Seriously was told that. Just wanted it gone so report looked nice. It would be karma if I am gone when this is resurrected, because that note will be gone as well as the project plan.
This place is a joke.


by
| 1891 views | | 1 reply (October 27) | Reply
Post ID: @OP+1k8k1xeh9

1 reply

I escalated this issue 2+ years ago to management. Was anything done, nope. Just keep on changing the dates manually and move on. They can do no wrong. Can’t wait to be gone.

by
| | Reply
Post ID: @aq+1k8k1xeh9

Post a reply

: